Copying alternative demand to the network
Alternative Demand values can be copied to a network, replacing network Customer Point and Node demand values.
Alternative Demand values can be copied to a checked out Network at any time. Copying Alternative Demand copies all Customer Point and Node demand information from the Alternative Demand to the Network.
To copy Alternative Demand values to a network:
- Associate the Alternative Demand with a Network. This can be done by dragging the Alternative Demand from the Model Group window or Explorer window into the GeoPlan Window.
- Select Copy Alternative Demand to Network from the Network menu to carry out the copying process.
Demand values in the Alternative Demand will overwrite
existing network demands.
No changes will be made to network Customer Points and
Nodes that do not have a corresponding record in the Alternative Demand.
Carry out validation
of the Network and Alternative Demand to check that the Alternative Demand
contains records for all Customer Points and Nodes in the network to be
updated.