Meshing the 2D Zone

Note

This stage assumes that you have started InfoWorks ICM and that the Explorer window is open, showing the Adding a 2D zone network icon. You should complete the previous stages before starting this stage. If you want to work with the prepared example data, load the appropriate version of the network. For instructions on how to load the database, see Opening the Example Database.

Back Back to previous stage.

The first step in adding a 2D zone is to digitise the zone polygon. Then, once digitised, the zone will need to be meshed.

This topic covers meshing of the 2D zone:

  1. Ensure that the Adding a 2D Zone network and the DTM ground model are both open on the GeoPlan.
  2. Use the Select tool to select the 2D zone. Then create a mesh by choosing Model | Meshing | Mesh 2D zones.... Drag the DTM ground model into the Meshing dialog and click OK.

    ClosedShow me!

  3. In the Schedule Job(s) dialog, set the mesh job to run on This computer and click OK.

    ClosedShow me!

  4. Open the Job Control window by clicking on the Job control window button (Job control window) of the Docking Windows toolbar. The Job Control Window displays the order and status of scheduled simulations and mesh jobs. When the status of the mesh job is Mesh ready click on the Status cell of the job in the Job Control Window.
  5. Select the mesh job in the Manage Mesh Results dialog and click the Load Mesh button to load the mesh onto the GeoPlan. Close the Manage Mesh Results dialog.

    ClosedShow me!

  6. Use the Properties tool on the river reach to check that the overlap between the bank and the 2D mesh has been created correctly. There should be no validation messages associated with the 2D zone or the connection to the left bank. If there are errors, adjust the shape, size or location of the 2D zone, then re-mesh the updated 2D zone. Repeat this process as necessary until all validation messages have cleared.

    ClosedShow me!

  7. The theme below can be used for bank edges to check that a bank edge is picked up by the 2D mesh.

    ClosedShow me!

  8. You can also check that a bank edge is picked up by the 2D mesh by looking in the meshing log or the mesh summary viewed from the 2D zone property sheet.

    ClosedShow me!

  9. Finally, use the Validation toolbar button to validate the whole model to ensure that changes have not introduced any accidental errors into the model.
  10. Every time a version-controlled item, such as the network, has been changed, it is good practice to commit the changes. Changes are stored in your own local copy of the network (in your Local Working Folder directory) and must be committed to the Master Database so that they become available to other users. Also, committing changes on a regular basis allows you to discard all the changes you have made since the last time you committed the network to the master database.
    1. In the Explorer window, right-hand click on the Adding a 2D Zone network and select Commit changes (save to master).
    2. The Commit change to server dialog is displayed.
    3. Type in any notes as appropriate.
    4. ClosedShow me!

    5. Click on OK to commit the changes and close the dialog.

You now have all the data you need to run a simulation.

Back to 2D Zone Tutorial main page.

Opening the Example Transportable Database

Committing Your Changes

Digitising Network Objects

Property Sheets

Object Properties Window